The timeline of planning and construction

July 1, 2015

Project conception

Two residents meet in a Bristol pub and agree to build a wind turbine. It is Bristol’s year as European Green Capital.

July 1, 2015
November 1, 2016

Land agreement

ACE starts to develop exclusivity agreement for the use of land with Bristol City Council which is ultimately signed in 2021.

November 1, 2016
August 1, 2019

Grid connection secured

This is timeline description. Please click here to change this description.

August 1, 2019
July 1, 2020

Planning approval granted

On the 8th July 2020, ACE’s planning application, supported by comprehensive and detailed environmental, ecological, transport, and community reports, receives a unanimous vote for approval from Bristol City Council’s Planning Committee. The permission is granted for 25 years from commissioning. 

July 1, 2020
November 1, 2021

Planning conditions met

Pre-construction planning conditions are met and approved by Bristol City Council, thus allowing the project to progress.

November 1, 2021
April 1, 2022

Financial close

The wind turbine receives loan funding from Thrive Renewables, Bristol & Bath Regional Capital, members of the Society of Merchant  Venturers, and a £0.5m grant from West of England Combined Authority (WECA) via the European Bank for Reconstruction and Development. 

April 1, 2022
June 1, 2022

Construction contracts are signed

Contracts are signed with Enercon Energy UK for the supply of the turbine and Knights Brown Ltd for the balance of plant (civil and electrical) work.

June 1, 2022
July 1, 2022

Groundwork commences

Work begins on site with clearance and the construction of access roads.

July 1, 2022
September 1, 2022

Foundation works begin

The 22 18m long piles are installed. The pile foundation is needed because the soil quality is very poor.
The initial steel reinforcement is placed to start the formation of the concrete foundation for the turbine.

September 1, 2022
December 1, 2022

Power Purchase Agreement signed

ACE signs a power purchase agreement with Bristol-based OVO Energy to sell the energy produced.

December 1, 2022
February 1, 2023

Blades and tower delivered

Two weeks after arriving in the UK, the three blades are delivered to the site with a police escort. The tower sections arrive two days later.

February 1, 2023
February 1, 2023

Blades and tower delivered

Two weeks after arriving in the UK, the three blades are delivered to the site with a police escort. The tower sections arrive two days later.

February 1, 2023
February 1, 2023

Tower, nacelle and rotor assembly

Following set up of the specialist crane, the tower sections are delivered and assembled and the nacelle and rotor are added over a four day period.

February 1, 2023
February 1, 2023

Blade installation

It then takes a further week to install all three of the blades.

February 1, 2023
March 1, 2023

Commissioning

The commissioning process begins to ensure the turbine is in working order.

March 1, 2023
May 1, 2023

Turbine fully operational

After six years the turbine is finally fully operational.

May 1, 2023