Timeline
July 2015
Project conception
Two residents meet in a Bristol pub and agree to build a wind turbine. It is Bristol’s year as European Green Capital.
Nov 2016
Land agreement
ACE starts to develop exclusivity agreement for the use of land with Bristol City Council which is ultimately signed in 2021.
Aug 2019
Grid connection secured
ACE secures a grid connection agreement with Western Power Distribution for an 11kV supply to the turbine site. The works include the provision and installation of high voltage cable and substation equipment.
July 2020
Planning approval granted
On the 8th July 2020, ACE’s planning application, supported by comprehensive and detailed environmental, ecological, transport, and community reports, receives a unanimous vote for approval from Bristol City Council’s Planning Committee. The permission is granted for 25 years from commissioning.
Nov 2021
Planning conditions met
Pre-construction planning conditions are met and approved by Bristol City Council, thus allowing the project to progress.
April 2022
Financial close
The wind turbine receives loan funding from Thrive Renewables, Bristol & Bath Regional Capital, members of the Society of Merchant Venturers, and a £0.5m grant from West of England Combined Authority (WECA) via the European Bank for Reconstruction and Development.
June 2022
Construction contracts are signed
Contracts are signed with Enercon Energy UK for the supply of the turbine and Knights Brown Ltd for the balance of plant (civil and electrical) work.
July 2022
Groundwork commences
Work begins on site with clearance and the construction of access roads.
Sept 2022
Foundation works begin
The 22 18m long piles are installed. The pile foundation is needed because the soil quality is very poor.
The initial steel reinforcement is placed to start the formation of the concrete foundation for the turbine.
Dec 2022
Power Purchase Agreement signed
ACE signs a power purchase agreement with Bristol-based OVO Energy to sell the energy produced.
Feb 2023
Blades and tower delivered
Two weeks after arriving in the UK, the three blades are delivered to the site with a police escort. The tower sections arrive two days later.
Feb 2023
Tower, nacelle and rotor assembly
Following set up of the specialist crane, the tower sections are delivered and assembled and the nacelle and rotor are added over a four day period.
Feb 2023
Blade installation
It then takes a further week to install all three of the blades.
March2023
Commissioning
The commissioning process begins to ensure the turbine is in working order.
May 2023
Turbine fully operational
After six years the turbine is finally fully operational.